Hi,
I am trying different ways of modeling scheduling problems,
and I have used cumulatives quite a lot because it has multiple resources,
and solves a large part of my problems.
but the i didn't find a way of specifying that
each resource can do only one task at a time.
Is there a good way to do this with cumulatives
or is it better to revert to unary and just
do a unary constraint for each resource ?
Or is it better to implement a propagator for this myself ?
(I am trying to achieve something similar to
http://www.emn.fr/z-info/sdemasse/gccat/Kassigning_and_scheduling_tasks_that_run_in_parallel.html
)